The National Land Commission (NLC) has clarified its role in compensating landowners affected by the construction of the Isiolo-Mandera highway after the World Bank raised concerns over delays in compensation along the route.
In a statement on Wednesday, November 18, NLC dismissed the blame being directed at it, maintaining that the majority of the work, which includes processing and disbursing compensation funds for affected landowners, is undertaken by the Kenya National Highways Authority (KeNHA) as directed by the World Bank.
According to the Commission, it is only mandated to conduct land valuations, verify assets, and prepare compensation schedules.
"The National Land Commission (NLC) wishes to clarify media reports regarding concerns raised by the World Bank over alleged delays in land valuation and compensation of Project Affected Persons (PAPs) under the Horn of Africa Gateway Development Project (HOAGDP)," NLC stated.
"It is worth noting that the Commission is only engaged in undertaking valuations and development of compensation schedules, with the role of processing of funds and disbursement of compensation funds to the PAPs being done by KeNHA as per World Bank directive and implementation of the HOAGDP," it added.
In a letter directed to Treasury Cabinet Secretary John Mbadi, Roads and Transport CS Davis Chirchir, and Lands CS Alice Wahome, Kenya's World Bank Division Director Qimiao Fan said land compensation has…