NLC Explains Ksh168 Billion Compensation Delays After World Bank Concerns

NLC Explains Ksh168 Billion Compensation Delays After World Bank Concerns

The highway, which is 60 per cent complete, has faced significant delays, with the World Bank revealing that the delays are costing the project up to Ksh1.2 billion in losses monthly.

The National Land Commission (NLC) has clarified its role in compensating landowners affected by the construction of the Isiolo-Mandera highway after the World Bank raised concerns over delays in compensation along the route.

In a statement on Wednesday, November 18, NLC dismissed the blame being directed at it, maintaining that the majority of the work, which includes processing and disbursing compensation funds for affected landowners, is undertaken by the Kenya National Highways Authority (KeNHA) as directed by the World Bank.

According to the Commission, it is only mandated to conduct land valuations, verify assets, and prepare compensation schedules.

"The National Land Commission (NLC) wishes to clarify media reports regarding concerns raised by the World Bank over alleged delays in land valuation and compensation of Project Affected Persons (PAPs) under the Horn of Africa Gateway Development Project (HOAGDP)," NLC stated.

"It is worth noting that the Commission is only engaged in undertaking valuations and development of compensation schedules, with the role of processing of funds and disbursement of compensation funds to the PAPs being done by KeNHA as per World Bank directive and implementation of the HOAGDP," it added.

In a letter directed to Treasury Cabinet Secretary John Mbadi, Roads and Transport CS Davis Chirchir, and Lands CS Alice Wahome, Kenya's World Bank Division Director Qimiao Fan said land compensation has…

In brief

The National Land Commission (NLC) has clarified its role in compensating landowners affected by the construction of the Isiolo-Mandera highway after the World Bank raised concerns over delays in compensation along the route. "The National Land Commission (NLC) wishes to clarify media reports regarding concerns raised by the World Bank over alleged delays in land valuation and compensation of Project Affected Persons (PAPs) under the Horn of Africa Gateway Development Project (HOAGDP)," NLC stated.

This is the opening of the story, shared with credit to Kenyans.co.ke. The rest of the report — with every detail — continues on the publisher’s website.

Continue reading at Kenyans.co.ke ↗

Cookie settings

Choose which cookies we may use. You can change this at any time from Cookie settings in the footer. Details of each cookie are in the Cookie Policy.

Strictly necessary

Needed for sign-in, security, payments and remembering these choices. Always on.

Preferences

Remember settings such as dark mode.

Analytics & performance

Help us count visits, understand which pages, devices and countries our readers use, and measure how well the site performs – anonymous and aggregated.

Advertising & marketing

Lets advertising partners show and personalise adverts, measure impressions, clicks and visits, prevent ad fraud and pay us – this is how the free site is funded.

🔔 News notifications

Get headlines from NewsHub on this device — even when the site is closed.

You can switch this off at any time. Works on Android, Windows, Mac and Linux browsers; on iPhone/iPad add the site to your Home Screen first.