Government tourism projects have taken years to complete while the bodies responsible for overseeing them lacked a comprehensive picture of whether they were being delivered efficiently, according to a State Comptroller's Office report published on Monday.The audit found that the Tourism Ministry, the Government Companies Authority, and three state-owned companies managing tourism infrastructure lacked the information needed to assess performance across projects, including whether they met deadlines and budgets and the quality of the work.The government's plan to consolidate those activities was itself based on incomplete preparatory work, the report found. Officials examined potential savings from a merger but did not assess the companies' performance or whether other ways of managing projects would work better.The companies oversee public tourism infrastructure - including promenades, parks, historic and religious sites, and urban tourist routes. They manage planning and hire contractors and supervise construction; meaning, they don't carry out the building work themselves. Their combined annual activity amounted to hundreds of millions of shekels in 2022-2025.The audit examined the Israel Government Tourist Corporation, the Dead Sea Preservation Government Company, and the Old Akko and Nazareth Development Company. It covered 68 projects carried out between 2010 and 2025, with expenditure totaling approximately NIS 377 million.Without a consolidated record to work from, the comptroller's office built its own database to examine project timelines and budgets.At…
Millions spent, years wasted: Israeli tourism projects face severe delays amid oversight failures
The audit found that the Tourism Ministry, the Government Companies Authority, and three state-owned companies managing tourism infrastructure lacked the information needed to assess performance.
In brief
Government tourism projects have taken years to complete while the bodies responsible for overseeing them lacked a comprehensive picture of whether they were being delivered efficiently, according to a State Comptroller's Office report published on Monday.The audit found that the Tourism Ministry, the Government Companies Authority, and three state-owned companies managing tourism infrastructure lacked the information needed to assess performance across projects, including whether they met deadlines and budgets and the quality of the work.The government's plan to consolidate those activities was itself based on incomplete preparatory work, the report found.
This is the opening of the story, shared with credit to The Jerusalem Post. The rest of the report — with every detail — continues on the publisher’s website.
Continue reading at The Jerusalem Post ↗


