Work is progressing on earthworks at Victoria Park for Brisbane's Olympic stadium, but the cost remains under wraps.
Deputy Premier Jarrod Bleijie has also revealed taxpayers will need to cover the cost of the demolition of the Gabba.
The Games Independent Infrastructure and Coordination Authority says it is in the final stages of the design of the National Aquatic Centre.
Early works at Brisbane's Victoria Park precinct are ahead of schedule, with construction on the stadium expected to begin mid-2027.
But the price tag for the substantial earthworks, ahead of the city hosting the 2032 Olympic and Paralympic Games, remains hidden.
It has also been revealed taxpayers will be slugged with the cost of the Gabba demolition.
Deputy Premier Jarrod Bleijie said 200,000 cubic metres of soil and rock had already been excavated.
"That is the equivalent of 80 Olympic swimming pools of dirt moved in 100 days in preparation for the Brisbane Stadium," he said.
"And in the middle, you will see two AFL footballs, and those two AFL footballs are the centre bounce for the Brisbane Lions' first game when the Brisbane Stadium opens."
Mr Bleijie was forced to defend the state government forking out $600 million in public funds to developers for the new Brisbane arena at Woolloongabba.