Topic:Electricity Production and Distribution
Electricity transmission service provider ElectraNet is facing uncomfortable questions over Thursday's blackout on the Eyre Peninsula.
The company spent $300 million on a network upgrade which it said would provide more reliable power.
ElectraNet says the transmission towers will be standing again "in a few months' time".
The owner of South Australia's high-voltage transmission network is facing uncomfortable questions over Thursday's blackout on the Eyre Peninsula, after pledging a $300 million network upgrade would provide more reliable power.
ElectraNet, the state's monopoly provider of electricity transmission services, has attributed the blackout to a "very unique, very rare" weather event that, at around 2.30pm on Thursday, damaged three transmission towers on the Eyre Peninsula.
The downed towers were located at Wharminda, a small rural locality that sits along a 270-kilometre transmission line between Port Lincoln and Cultana.
ElectraNet spent $300 million on the high-voltage line, constructing 500 new transmission towers and upgrading five substations.
The project, named Eyre Peninsula Link, was completed in March 2023.
In a media release heralding its opening, ElectraNet CEO Simon Emms said it would give "residential and business electricity users a more secure and reliable power supply".
But the blackout that unfolded over Thursday afternoon and into Friday left ElectraNet fielding uncomfortable questions from residents, cabinet ministers and the media about how…