Before renovation, Olkaria I was generating approximately 45MW.
Kenya Electricity Generating Company (KenGen) has injected an additional 63.3MW into the national grid following the successful rehabilitation of the country’s oldest geothermal power station, Olkaria I.
The power plant, commissioned in 1981, has been undergoing an extensive three-year rehabilitation programme.
The move comes at a time when the country’s power demand has risen sharply against limited production, raising fears of a power crisis in the coming years.
According to KenGen MD Engineer Peter Njenga, before the renovation works began, the facility was generating approximately 45MW.
He said that trials were underway at the plant, which would officially be commissioned by President William Ruto on December 7, 2026.
“We are happy to announce that the rehabilitation works of Olkaria I are now complete, and we have injected an extra 63.3mw into the national grid,” he said.
Njenga was addressing the press in Naivasha after a clean-up ahead of the three-day sustainable energy conference in the geothermal-rich area Olkaria region.
He said that the power generating company would use the conference to meet financiers because some of the projects that they intended to embark on required huge resources.
“We are going to tell our financiers the projects that we are embarking on for the next number of years and the resources that we…