Treasurer Eric Abetz has appeared at a parliamentary committee to answer questions on cost increases for the Macquarie Point stadium.
He confirmed it is set to proceed even if the state cannot secure extra funding, and that a state spending cap will be exceeded.
The final construction contract is scheduled to be signed on December 18.
The Tasmanian government says it will proceed with the Macquarie Point stadium even if it does not receive more funding from the Commonwealth or AFL in response to increasing cost estimates.
The government has also not set a maximum borrowing limit and has conceded that it has not kept its written commitment with an independent MLC to stick to its $875 million cap on the state's contribution.
The government's cost estimate for the stadium increased from $1.13 billion to $1.23 billion, with the Commonwealth contributing $240 million to the broader precinct and the AFL adding $15 million.
The final cost rises to $1.54 billion once precinct and development costs are included.
Treasurer Eric Abetz and senior departmental staff answered questions at a parliamentary committee today, which included updates on negotiations with tenderers that are soon to conclude.
It was confirmed that the contract will be fixed price, rather than cost-plus.