Kenya’s oldest geothermal power station is back in operation following a three-year rehabilitation programme that has increased its electricity generation capacity, giving the national grid an additional 63.3 megawatts (MW).
The Kenya Electricity Generating Company (KenGen) announced the completion of works at Olkaria I power station in Naivasha, Nakuru County, which was commissioned in 1981.
Before the rehabilitation, the facility had an installed capacity of 45MW. The upgrade has increased its capacity to 63.3MW, adding more electricity to the national grid at a time when Kenya is experiencing growing demand from homes, businesses and manufacturing industries.
KenGen Managing Director Peter Njenga said the rehabilitation was complete and the facility was undergoing tests before its official commissioning.
President William Ruto is expected to officially commission the upgraded plant on December 7, 2026.
The project involved extensive repairs and replacement of ageing equipment at the facility, which has been operating for more than four decades. The improvements are expected to extend its useful life by more than 25 years.
Olkaria I holds a special place in Kenya’s energy development because it was the first geothermal power station in the country and among the earliest of its kind in Africa. Its commissioning in 1981 marked the beginning of commercial geothermal electricity generation in Kenya.