The National Land Commission (NLC) has attributed delays in securing land ownership documents for Affordable Housing projects to missing reports and supporting paperwork from the Affordable Housing Board (AHB).
Appearing before the Parliamentary Committee on Housing, Urban Planning and Public Works on November 26, NLC Director of Land Administration and Management Samuel Mwenje said the commission was still awaiting key documents needed to process additional project sites.
He disclosed that the NLC had issued 12 letters of allocation covering previously unalienated public land and processed 11 consents to transfer parcels registered under other public institutions.
The committee expressed concern that the prolonged delays could affect Kenyans seeking legal ownership of houses they had subscribed to and paid for.
Buuri MP Rindikiri Mugambi insisted that buyers needed proper documentation to establish their ownership rights and benefit from their investments.
“You cannot claim to have a house or even a floor without documentation. We need to fast-track it so that Kenyans can enjoy what they have saved for and what they have paid for,” he said.
Mwenje explained that the processing timelines varied because individual sites had different ownership arrangements, existing land uses and legal requirements.
He assured Members of Parliament that the Commission was prepared to accelerate the remaining work once the necessary information was submitted.