The Rironi-Naivasha section of the 233-kilometre Rironi-Mau Summit Highway will be opened by December 20, 2026, Treasury Principal Secretary Chris Kiptoo has announced.
Speaking after inspecting the ongoing works along the section on Sunday, November 29, Kiptoo said the works along the section was progressing well as contractors rush to open the 59-kilometre section to traffic on the said date.
According to the PS, the opening of the section would ease traffic congestion that has been traditionally experienced along the route, especially during festive seasons like now.
"The Construction of the Nairobi - Nakuru - Mau Summit Highway, a project being implemented through the Public-Private Partnership (PPP) framework, has progressed steadily since works commenced on 28th November 2025," Kiptoo stated.
"Selected sections of the highway are scheduled to be opened to traffic by December 20, 2026, to improve traffic flow and ease the congestion traditionally experienced along this busy transport corridor during the festive season," he added.
So far, 41.5 kilometres of earthworks have been completed along the 59-kilometre section, with construction of bridges, interchanges, drainage structures and road pavements also at an advanced stage.
"Along the 59-kilometre Rironi - Naivasha section (A8), which is being expanded into a four-lane dual carriageway, 41.5 kilometres of earthworks have so far been completed, with construction of bridges, interchanges, drainage structures and road…